Case study

University of Oklahoma Headington Tennis Center

18 courts, 12 outdoor and 6 indoor. Laykold. Competitive public RFP. Six courts in play for the team through the whole program.

18courts resurfaced
12 + 6outdoor courts at Headington, indoor courts at the Gregg Wadley facility
6courts kept in play at all times, an owner requirement
2026USTA Outstanding Facility, awarded to the complex and announced by OU in September 2026

The project

The University of Oklahoma put the resurfacing of its entire tennis complex out to competitive bid in 2026: the 12 outdoor courts at the Headington Tennis Center and the 6 indoor courts at the Gregg Wadley facility. EliteTrax Sports Surfaces was awarded the contract in June 2026 and the courts were finished and in use for the fall season.

Scope

  • Full acrylic resurfacing system in Laykold on all 18 courts and connecting paths
  • Crack treatment and preparation on every court
  • Red playing areas with green surrounds, matched indoor and outdoor
  • OU marks stenciled to the University's specification
  • Phased so six courts stayed available to the program throughout

What it took

An SEC program does not shut down for a contractor. The work was sequenced in phases around team use, with the indoor and outdoor scopes scheduled so the athletic department always had six courts. Oversight came from our Technical Director, Kevin Leach, CTCB, ASBA Certified Court Builder.

The outcome

On September 2, 2026 the University announced that the Headington and Wadley complex had been named a 2026 USTA Outstanding Facility. The award belongs to the University and its facility; we are glad the courts were ready for it.

OU Athletics and OU Procurement are both available as references for public and institutional buyers. Ask when you request a bid package.

In progress to finished

What the courts looked like along the way

Site photos from the crew during the program, next to the finished product. Every public project gets daily photo records like these.

Outdoor courts at OU Headington with acrylic resurfacer going down before the color coats, grandstand and Sooners windscreen behind
In progress Outdoor courts, resurfacer coats down, color coats next.
Indoor court at the Gregg Wadley facility with the red playing area freshly squeegeed and the green surround going on
In progress Indoor courts, red playing area down, green surround going on.
Finished indoor court at OU centered on the net with new lines and nets in place
Finished Indoor court lined, netted and back to the team.
Gallery

Headington and Wadley, finished

Finished-court photography: Nicholas Quinnie for EliteTrax Surfaces, 2026. Progress photos: EliteTrax crew.

Running a university or school tennis program?

We will give you a realistic scope and budget number for your courts, phased around your season.

Call 817.349.6847Get a budget number